Local · Columbia County, Georgia · Friday, November 13, 2026

Developing storyThe final agreement terms, the November homestead tax relief vote outcome, and the timing of the first payment may still change.
SHARED WITH YOU

Columbia County approves data center agreement with Google affiliate for annual payments and tax relief

Columbia County's Economic Development Authority approved a memorandum of understanding with a Google subsidiary for a data center project of at least $17 billion, which would pay the county $40 million a year for seven years.

Columbia County, Georgia Power and Google announced a partnership in July that sets development rules for data centers in the county. The framework covers decibel and lighting limits, a smaller physical footprint, protections for the local water supply, and a plan for the site at the end of its useful life. Google is slated to be the sole operator of the Columbia County Data Center in Appling, and it has committed to paying all energy costs tied to the project. Georgia Power says it will keep rates stable through 2028.

In late August, the county's Economic Development Authority approved the memorandum of understanding with Kinetic Infrastructure Solutions, which is an Alphabet subsidiary. County Manager Scott Johnson said the county would receive $40 million a year for seven years, and the authority would receive about $5 million a year. The county currently collects roughly $25 million a year in homestead property taxes, and the county's stated goal is to eliminate its share of those taxes. Johnson said the homestead tax relief grant would need voter approval.

Some details are still open. Officials expect the first payment by the end of 2026 or early 2027, and the final terms are described differently across outlets. The agreement's noise limits are also described with a specific number in some outlets but not in the county's announcement.

Cited facts

  1. Columbia County, Georgia Power and Google announced a partnership on data center development standards on July 23, 2026.

  2. The standards include decibel limits, lighting rules, a minimal physical footprint, water supply protections and an end-of-life plan for the facility.

    ✓ 1WJBF
  3. Google will be the sole operator of the Columbia County Data Center in Appling, and it has committed to paying 100% of the project's energy costs.

  4. The Economic Development Authority of Columbia County approved an agreement representing a commitment of at least $17 billion, with Kinetic Infrastructure Solutions, an Alphabet subsidiary.

  5. The county is set to receive $40 million a year for seven years, and the Development Authority about $5 million a year.

  6. The county currently collects about $25 million a year in homestead property taxes, and the tax relief grant depends on voter approval.

Where reports differ

The county's July announcement gave no numeric decibel limit, while ConstructionReview Online reported a 65-decibel ceiling and CryptoBriefing reported a 65-decibel ceiling plus a 500-foot buffer from residential areas.

WRDW reported the first payment was expected at the end of this year or early next year, while WGAC wrote the first payment was expected by the end of this year or in early 2025.

The Columbia County Observer reported that county officials projected $12.1 billion in net public revenue over 35 years, with $4.4 billion for the county and $7.7 billion for the school district after incentives and public costs; the school district does not share in the $40 million annual payment.

Columbia County Together, a local Substack, argued that the July agreement is a negotiated deal with one end user rather than county law, and that it could end when the contract does, unlike the county's data center ordinance.

Perspectives: how each side framed it

PLUSPRO

See how left, center, right and international outlets framed this story, and which claims only some of them reported.

Unlock with Plus · $4.99/mo

Checked outlets

9 outlets · 9 center. Each opens the outlet's own article.

Something look off? Tell us

Baseline checks the day's top stories across the spectrum

Every morning: the facts outlets on the left, center and right agree on, with every one linked to its source.

The Baseline newsletter

The morning's facts in your inbox: the top national and global stories, with cited facts. Free on every plan. Signing up also creates your free Baseline account.